Re: Milestone Billing Structure

$
0
0

Hi,

 

Another Suggestion is:

 

1) Create a Project with 100 WBS & each WBS will be treated as a Villa.

2) Create NWA for (Engineering & design, Land preparation and Construction etc.)

3) Assign materials to these NWA.

4) Assign Sales order to Each WBS for each villa order/cost.

5) Settle your actual cost of Project either to cost center or Final Asset.

 

Also lets wait for other expert's suggestions.

 

 

Regards

Shishir