Hi,
I know there are number of posts in the forum on this topic. But I could not find my answer in them.
So please help me understand the reorder point SAP is calculating.
I have a material with following data:
MRP type = V2 (Automatic reorder point calculation)
Planned delivery time = 3 days
GR processing time = 0
Safety stock = 0
Service level = 0
Forecast model = G (Moving average model)
Period indicator = W
Historical period = 9
Forecast period = 1
Consumption values = 3,4,5,6,7,8,9,10,11
SAP gives me the result as below:
Forecast = 7 (Matches with my calculation)
Safety stock =0 as service level not maintained (I agree)
Reorder point = 6
My calculation is, reorder point = SS+ forecasted requirement during replenishment lead time
= 0 + 7 * (3/7) = 3
Why SAP has calculated 6 instead of 3 ?