Difficulties in Reorder point calculation

$
0
0

Hi,

I know there are number of posts in the forum on this topic. But I could not find my answer in them.

So please help me understand the reorder point SAP is calculating.

 

I have a material with following data:

MRP type = V2 (Automatic reorder point calculation)

Planned delivery time = 3 days

GR processing time = 0

Safety stock = 0

Service level = 0

 

Forecast model = G (Moving average model)

Period indicator = W

Historical period = 9

Forecast period = 1

Consumption values = 3,4,5,6,7,8,9,10,11

 

SAP gives me the result as below:

 

Forecast = 7 (Matches with my calculation)

Safety stock =0 as service level not maintained (I agree)

Reorder point = 6

 

My calculation is, reorder point = SS+ forecasted requirement during replenishment lead time

                                                 = 0 + 7 * (3/7) = 3

 

Why SAP has calculated 6 instead of 3 ?

 

Thanks in advance.