Hi Experts,
Is there is any way that we can default the future validity period price on the SA's are same as the current validity period price? Our system went live in 2010 and we get new prices for each material every 6 months and it will be valid for 6 months. incase if we are not getting price from the supplier on time and the current validity period expires, system takes the price from the validity period ending in year 12/31/9999. system automatically pick the initial price for this validity period. example below:
validity start Validity end Price
01/01/2010 06/30/2010 100
07/01/2010 12/31/2010 90
01/01/2011 06/30/2011 75
''
''
01/01/2013 06/30/2013 48
07/01/2013 31/12/9999 100 with deletion indicator
our business wants to get the $ 48 in to the future validity period. is there anyway to get this done ?
Best regards
Sibi Dominic