Re: WBS-element field in Reservation

$
0
0

Yerzhan,

 

What type of Project Stock are they selecting on the Project Header?  This has a very large impact on this discussion.

 

If your customer has selected valuated project stock they must do a GI from inventory to the project for the costs to hit the project, otherwise the costs stay in inventory.

 

I would not create manual reservations if you cna avoid it because someone will always forget to create them and the MRP calculations will be messed up.

 

Ken