Re: How to use different planning calendars at location-product level in SNP Heuristics

$
0
0

Hi, not sure whether BADI /SAPAPO/SNP_GET_DATE is the desired one (will need note 1796539), but I think you'd better use period lot size in such case, instead of controlling the production calendar with BADI. Another option would be assign the calendar to the production resource (to use this, you'll need to set 'Heu:Resource Cal.' to 'consider resource calendar' in SNP global settings.